1/19/15 This weeks work was much like the past several weeks - TopicsExpress



          

1/19/15 This weeks work was much like the past several weeks in regards to projects being worked on. Some new news for all the brake shoe donors is that all the shoes have now been delivered. Likewise for the tube and flue donors those parts are now being inserted into the boiler. Fifty tubes and flues were cut and slid into place. Welchs Boiler Service will begin the expanding work in February. This gives us enough time to get them all in place. Randy Mc. and Pete O. began laying out the painted conduits for the cab electrical work. It should begin taking shape in the next few work sessions. Hope to see you at the site this week...and as usual, Keep on Steamin, Rick Kirby CMO, NMSL & RHS
Posted on: Tue, 20 Jan 2015 02:25:31 +0000