BOHOL POWER SUPPLY UPDATE Restored transmission services in parts of Bohol 27 NOVEMBER 2014 NGCP MEDIA ADVISORY. NGCP restored transmission services to BOHECO IIs Alicia and Guindulman Substations after re-energizing at 3:41PM the 69kV Ubay-Alicia-Garcia line up to structure no. 168 (Ubay-Guinacot, Guindulman). NGCP power transmission service to all its customers in Bohol is now 100 percent normal (end)