H.A Dhihdhoo Housing project Updates Highlight of Construction - TopicsExpress



          

H.A Dhihdhoo Housing project Updates Highlight of Construction Status Structural - setting footing completed 200 house - concrete ground beam completed 200 house - concrete slab completed 200 house - concrete column completed 200 house - setting roof beam completed 200 house Architectural - roofing sheet completed 86 house - internal brick work completed 101 house - external brick work completed 153 house - internal plastering work completed 38 house - external plastering work completed 29 house - touch-up painting wall completed 4 house
Posted on: Mon, 09 Sep 2013 04:28:31 +0000