Linskey Construction, Inc. has provided the following update on - TopicsExpress



          

Linskey Construction, Inc. has provided the following update on the Gateway Center project at Boston and Bridge Street: The contractor intends to mobilize to begin processing the material for placement of the surcharge fill. On-site activities will be as follows: Mobilize on 6/23 Process material for crushing 6/23-6/25 Crush material for use at surcharge 6/25-7/1 This will be followed by the placement of on-site processed material and importing of the remainder of the fill required at the surcharge. The contractor will work within the City’s work hours and shall manage dust through the use of the water truck that is currently on-site.
Posted on: Fri, 20 Jun 2014 16:23:04 +0000