Matts project is halfway through its delivery schedule. Although there have been delivery issues, most of them have not had much variations. Matt wants to determine how much work is still left in the project. Which is the most accurate way to determine the remaining work to be carried out by the project team? 1. Earned Value Technique 2. Manual forecast 3. Force-Field analysis 4. Rolling wave method