Progress Report #4 - VOM FASS Oils Vinegars Spices I am excited to announce that we are 2-3 weeks away from completion of the store build out. Habitat Construction has made wonderful progress on the interior finish work. We are scheduled to have the flooring and lighting delivered on October 8th. We have also confirmed that our fixtures (cash wrap, counters and shelving) will finally arrive on October 20. VOM FASS USA representative will be in store on the 20th to begin installing the new fixtures. That said, we have set the date to open the doors on November 1. We are also scheduling a fantastic series of events for our Grand Opening on Nov 20 - 23. Stay tuned for more details.