Projects under EPC Implementation: Nitrogen Gas Injection (Pure - TopicsExpress



          

Projects under EPC Implementation: Nitrogen Gas Injection (Pure Case) The project envisages revamping of one of the existing Injection Compressors at Habshan 3 (Unit 394) to handle pure nitrogen and installation of a new Injection Compressor at Habshan 1(Unit 98) to inject pure Nitrogen (600 MMSCFD) in the northern area of Thammama ‘F’ reservoir, after reconfiguring the residue gas injection system at ADCO side. EPC Contract for the project was awarded in Oct’ 2011 to SAMSUNG. Engineering and Procurement activities for the Project are in progress. The new facilities are planned to be completed and operational in phases by Q4, 2013 and Q3, 2014 respectively.
Posted on: Sun, 15 Sep 2013 10:08:15 +0000