Q: What construction work will happen during the closure? A: - TopicsExpress



          

Q: What construction work will happen during the closure? A: During the closure, contractors will connect both ends of the bridge with I-80. At Yerba Buena Island, the transition structure into the tunnel is complete, so crews will be installing traffic barriers, laying connecting pavement and striping lanes. On the Oakland side, contractors will demolish a portion of the existing eastbound touchdown and will construct new eastern lanes. Crews will also install a temporary wooden bike path. Additional work includes paving, striping and erecting barrier rail, as well as routine maintenance on the West Span.