Question No : 27 As a project manager, you are responsible for meeting the project schedule deadlines. If there is some delay in the project schedule, you should (choose the most appropriate answer): Choice 1. Increase the timeline for the project. Choice 2. Fast track or crash the project, and let the management know the impact of this action. Choice 3. Ask the resources to work overtime to meet the project deadlines. Choice 4. Change the project scope.