Question No : 31 You are the project manager in an automobile manufacturing company. Machine parts required in your manufacturing process supplied by a vendor did not reach in time because of heavy rains. You had anticipated this risk and planned for it in your risk response plan. So, as per your risk response plan, you started using unutilized machine parts supplied one year ago. However, this has subjected your project to a new risk - the machine parts which were not used for one year suffer from higher level of defects. This new risk can also be called: Choice 1. Unidentifiable risks Choice 2. Unmanageable risks Choice 3. Secondary risks Choice 4. Residual risks