SNo. Particulars of items Quantity Perday 1. Brick work in lime - TopicsExpress



          

SNo. Particulars of items Quantity Perday 1. Brick work in lime or cement mortar in foundation and plinth 1.25cum (45cuft)per mason 2. Brick work in lime or cement mortar in superstructure 1.00cum (35cuft)per mason 3. Brick work in mud mortar in foundation and plinth 1.50cum (55cuft)per mason 4. Brick work in mud mortar in superstructure 1.25cum (45cuft)per mason 5. Brick in cement or lime mortar in arches 0.55 cum (20cuft)per mason 6. Brick in cement or lime mortar in jack arches 0.55 cum (20cuft)per mason 7. Half brick wall in partition 5.00sqm (50sqft)per mason 8. Coursed rubble stone masonry in lime cement mortar including dressing 0.80cum (30 cuft)per mason 9. Random rubble stone masonry in lime or cement mortar 1.00cum (35cuft)per mason 10. Ashlars masonry in lime or cement mortar 0.40cum (15cuft)per mason 11. Stone arch work 0.40cum (15cuft)per mason 12. Lime concrete in foundation or floor 8.50cum (300cuft)per mason 13. Lime concrete in roof terracing 6.00cum (200cuft)per mason 14. Lime concrete 1:2;4 5.00cum (175cuft)per mason 15. RB work 1.00cum (35cuft)per mason 16. RCC work 3.00cum (125cuft)per mason 17. 12mm (1/2) plastering with cement or lime mortar 8.00sqm (80sqft)per mason 18. Pointing with cement or lime mortar 10.00sqm (100sqft)per mason 19. White washing or colour washing coats 70.00sqm (700sqft)per white washer 20. White washing or colour washing coats 200.00sqm (2000sqft)per white washer 21. Painting or varnishing doors or windows one coat 25sqm (250sqft)per painter 22. Coal tarring or soligum painting one coat 35.00sqm (350sqft)per painter 23. Painting large surface one coat 35.00sqm (350sqft)per painter 24. Distempering one coat 35.00sqm (350sqft)per painter 25. 2.5cm(1’) CC floor 7.50sqm (75sqft)per painter 26. Flag store floor laying with lime or cement mortar excluding LC 10.00sqm (100sqft)per painter 27. Brick on edge in floor lime or cement mortar excluding LC 7.00sqm (70sqft)per painter 28. Brick bat floor as in above 8.00sqm (80sqft)per painter 29. Timber framing sal or teak wood 0.07cum (2.5cuft)percarpenter 30. Timber framing sal or country wood 0.15cum (5cuft)per carpenter 31. Door and window shutters paneled or glazed 0.15sqm (7sqft) per carpenter 32. Door and window shutters paneled or battened 0.80sqm (0.80sqft)percarpenter 33. Sawing hard wood 4.00sqm (40sqft) per pair of sawers 34. Sawing soft wood 6.00sqm (60sqft) per pair of sawers 35. Single allahabad tiling or mangalore tiling 6.00sqm (60sqft) per tile layer 36. Double allahabad tiling 4.00sqm (40sqft) per tile layer 37. Breaking of brick ballest 40mm (11/2”) gauge 0.75cum (35cuft)per labourer or breaker 38. Breaking of brick ballest 25mm (1”) gauge 0.55cum (20cuft)per labourer or breaker 39. Breaking of stone ballest 40mm (11/2”) gauge 0.40cum (10cuft)per labourer or breaker 40. Breaking of stone ballest 25mm (1”) gauge 0.25cum (10cuft)per labourer or breaker 41. Ashlar stone dressing 0.70cum (25cuft)perstonecutter 42. Flag stone dressing 1.50sqm (25sqft)perstonecutter 43. Earthwork in excavation in ordinary soil 3.00cum (100cuft)per belder mazdoor 44. Earthwork in excavation in hard soil 2.00cum (75cuft)per belder mazdoor 45. Excavation in soil 1.00cum (35cuft)per belder mazdoor 46. Number of bricks laid by a mason in brick work upto a height of 3m(10”) 600 bricks per mason 47. Amount of work done by a mazdoor helper per day Mix 3.00cum (100cuft)mortar per mazdoor Deliver brick 4000 nos to a distance of 15m (50”) per mazdoor Deliver mortar 5.5cum (200cuft) per mazdoor 48. Scaffolding cost for single storey building Re.0.50per cum (Rest.1.5%cuft) of brick work. Items 46,47 and 48 are based on the committee report on rates and cost government of India. LABOUR (MAZDOOR) REQUIRED FOR DIFFERENT WORKS Extracts from the report on productivity projects in building industries issued by National Building Organisation are given below:- a) Earthwork per 28.30 cum (12000cuft) 1) Excavation in foundations, trenches etc., in ordinary soil including disposal up to 30m (100’) and lift of 1.5m (5ft) –5 beldars and 4 mazdoors can do 28.30 cum (1000cuft) per day. 2) Refilling excavated earth in foundations, pointh etc, including consolidation in 15cm(6”) layers-3 beldars, 2 mazdoors and ½ bhisti can do 28.30 cum (1000cuft) per day. 3) Disposal of surplus earth within a lead of 30m (100’)-1 mazdoor can do 2.83cum (100 cuft) per day. b) Cement concrete work per 2.83 cum (100cuft) laying cement concrete – 2 beldars, 3 mazdoors, ¾ bhisti and ¼ mason, can do 2.83 cum (100 cuft) per day. c) R C C work:- 1) Laying reinforced concrete – 3 beldars, 3 mazdoors, 1½ Bhisti and ½ mason can do 2.83 cum (100cuft) per day. 2) Centering and shuttering for flat surfaces – 4 beldars and 4 carpenters (II class) can do 9.6sqm(96sqft) per day. 3)Reinforcement work for R C C –1 blacksmith or fitter and 1 beldar can bend and place in position 1 quintal (2 cwt) of steel per day. d) Stone work per 2.83 cum (100cuft)- Random rubble masonry with blue stone in foundations-3 masons, 3 beldars, 2 mazdoors and 1/4bhisti can do 2.83 cum (100cuft0 per day e) Brick work per 2.83 cum (100cuft)- First class brick work in 1:4 cement mortar in superstructure partition walls, junctions of roof, parapet walls and string course – 2½masons,4½ mazdoors and 1/2 bhisti can do 2.83 cum (100cuft) per day. F) Wood work :- 1) For the frames of doors and windows –2 carpenters and 1 beldar can work 0.18 cum (6.40cuft) of wood equivalent to door frames 7.5cm x 10m of 1.2m x 2.1m (3’x4’of 3’x11’x7’)size per day. 2) For paneled, glazed, etc, shutters-15 carpenters and 4 beldars can make and fix 4 shutters 40 mm thick of size 2.00m x 1.15m (1 ½ thick of size of 6’-9x 3’-9’) per day. Quantity of wood per shutter – 0.075 cum, ie2.66 cuft. g) Iron work :- 1) Fixing 40mm x 3mm=38cm(1 ½ “ x ½ ‘x 15”0 flat iron holdfasts-1 blacksmith (II class), I mason and I beldar can fix 36 holdfasts per day. 2) Fixing 16mm dia. 5/3” dia) M S rods –1 blacksmith (II class), 2 carpenters (II class) and 3 mazdoors can fix 16.5m (54rft) per day. h) Flooring: - 4cm thick (1 1/2 “)thick cement concrete flooring of 40sqm (400sqft) require 5 masons, 4 beldars, 3 mazdoors and 1 bhisti per day for mixing laying and finishing. I) Finishing :- 1) Plastering with any mortar 12mm (5”) thick – 3 masons, 3 mazdoors and 1 bhisti can plaster 40sqm (400a ft) per day. 2)White washing or colour washing (3 coats) – 1 white washer and 1 mazdoor can do 60sqm (600sqft) per day. 3) Painting two coats such as chocolate, red, grey, etc on wood are steel –3 Painters and 2 mazdoors can paint 10sqm (100sqft) per day. LOAD FOR A TWO –BULLOCKS CART Quantity or Number Sl# Particulars of materials On Kachcha Road On Pucca Road 1. Brick 19 cm x 9cm x 9cm 275nos 400nos 2. Brick ballast 0.85 cum (30cuft) 1.10 cum (40cuft) 3. Stone ballast 0.70 cum (25 cuft) 1.00 cum (35cuft) 4. Kankar 0.85 cum (30cuft) 1.10 cum (40cuft) 5. Sand surkhi 0.85 cum (30cuft) 1.10 cum (40cuft) 6. Lime 1.10 cum (40cuft) 1.40 cum (50cuft) 7. Tiles Allahabad or Mangalore 275nos 400nos 8. Cement 15bags 20 bags 9. Steel 0.75 tonne 1 tonne Note; A bullock ……..carry about one tonne load. The average speed for a bullock cart may be taken as 3.20km (2 units) per hour and ¾ hour may be allowed for loading and unloading. Taking 8 hours working per day, the number of trips per day, can be calculated. LOAD FOR TRUCKS ON PUCCA METALLED ROAD – Trucks3 tonners 5 tonners8 tonners diesel truck Brick or Allahbad tiles or Mangalore tiles1000nos 1500nos2000nos Cement, steel and other Heavy materials 3 tonne 5 tonne8 tonne Other materials – Ballast, Kankar, grit Sand coal, etc., 2.8cum 4.20cum5.6cum (100cuft) (150cuft)(200cuft) On kachcha earthen road the load will be less by 33 per cent. MATERIALS FOR DIFFERENT ITEMS OF WORKS The requirement of materials for different items of works is as given below:- Sl# Particulars Quantity 1. Bricks (9” x 4 ½ “ x3” or 20 cm x 10cm x 10cm nominal size) for brick work 1350 nos for 100cuft 50000 nos per % cum (500nos.per cum) 2. Dry mortar for brick work 30% 30cuft for 100 cuft 30cum for 100 cum 3. Stone for rubble stone masonry 125% 125cuft for 100 cuft 125cum for 100 cum 4. Dry mortar for rubble stone masonry 42% 42cuft for 100 cuft 42cum for 100 cum 5. Bricks for brick ballast for lime concrete 1050cuft for 100 cuft 37000cum for 100 cum 6. Brick bats or brick ballast for lime concrete 150cuft for 100 cuft 150cum for 100 cum 7. Brick ballast for lime concrete 100cuft for 100 cuft 100cum for 100 cum Sl# Particulars Quantity 8. Dry mortar for lime concrete I foundation and floor 35% 35cuft for 100cuft 35cum for 100 cum 9. Dry mortar for lime concrete in roof terracing 45% 45cuft for 100cuft 45cum for 100 cum 10. Materials for cement concrete 1:2:4 Ballast or grit 88% 88cuft for 100cuft 88cum for 100 cum Sand 44% 44cuft for 100cuft 44cum for 100 cum Cement 22% 22cuft for 100cuft 22cum (60 bags)for 100 cum 11. Materials for 2.5cm (1”)cc 1:2:4 floor Stone grit 8cuft for 100sqft 2.40cum for 100 cum Sand 4cuft for 100sqft 1.20cum for 100 cum Cement 2 ¼cuft (2 bags) for 100cuft 0.08cum (24 bags)for 100 cum 12. Bricks for R B work 1200 nos for 100cuft 42000nos/% cum(420 mps.[er ci,) 13. Dry mortar for R B work 45% 45cuft for 100cuft 45cum for 100 cum 14. Dry mortar for 12mm (1/2) plastering 6cuft for 100sqft 2.00cum for 100 sqm 15. Dry mortar for pointing in brickwork 2cuft for 100sqft 0.60cum for 100 sqm 16. Lime for white washing one coat 1kg for 100sqft 10kg for 100 sqm 17. Dry distemper for ist coat 0.65 kg for 100sqft 6 ½ kg for 100 sqm 18. Dry distemper for 2nd coat 0.50 kg for 100sqft 5kg for 100 sqm 19. Snow-Cem for Ist coat 3kg for 100sqft 30kg for 100 sqm 20. Snow-Cem for 2nd coat 2kg for 100sqft 20kg for 100 sqm 21. Paint ready mixed for painting one coat 1/3gl.for 100sqft 10ltr for 100 sqm 22. Paint (stiff) for painting one coat 1kg for 100sqft 10kg for 100 sqm 23. Bricks (20 x 10 x 10cm) for brick floor or half brick wall 500 nos for 100sqft 5000nos.for 100sqm 24. Dry mortar for brick floor or half brick wall 12cuft for 100sqft 3.20 cum for 100 sqm 25. Bricks (9” x 4 ½ “ x3”) for brick flat work 350 nos for 100sqft 3500nos.for 100sqm 26. Dry mortar for brick flat floor 8cuft for 100sqft 2.25cum for 100 cum 27. Bricks (9” x 4 ½ “ x3”) required for honey comb wall 325 nos for 100sqft 3250 nos.for 100sqm 28. Dry mortar for honey comb wall 8cuft for 100sqft 2.5cum for 100 cum 29. Materials for 2cm (3/4”)thick damp proof course of 1:2 cement mortar Cement 3cuft (2.5bags) for 100sqft 0.90cum (27 bags)for 100 cum Sand 6cuft for 100sqft 1.80cum for 100 cum Compound or impermo @ 1kg per bag of cement 2.5kg for 100sqft 27kg for 100 sqm 30. Materials for 2.5cm (1”)cc 1:1 ½ :3 damp proof course Stone grit 8cuft for 100sqft 2.25cum for 100 cum Sand coarse 4cuft for 100sqft 1.13cum for 100 cum Cement 2 ½ cuft (2 ½ bags) for 100sqft 0.75cum for (221/2bags)for100 cum Compound or impermo @ 1kg per bag of cement 21/2 kg for 100sqft 22½ kg for 100 sqm 31. Bitumen or asphalt for painting on D P C or on roof – 1st coat 15 kg for 100sqft 150 kg for 100 sqm 2nd coat 10 kg for 100sqft 100 kg for 100 sqm 32. G G I sheet for roof 128sqft for 100sqft 128 sqmfor 100sqm 33. A G corrugated sheet for roof 115sqft for 100sqft 115 sqmfor 100sqm 34. Timber for paneled door shutter 4cm (1 ½”) thick 15cuft for 100sqft 4.5 cum for 100 cum 35. Timber for battend door shutter 4cm (1 ½”) thick 13cuft for 100sqft 4.0 cum for 100 cum 36. Timber for paneled & glazed shutter 4cm (1 ½”) thick 11cuft for 100sqft 3.0 cum for 100 cum Timber for fully glazed shutter 4cm (1 ½”) thick 8cuft ( Rinku sk)
Posted on: Fri, 23 Jan 2015 09:08:27 +0000

Trending Topics



Recently Viewed Topics




© 2015