The auditor found the cost of killing the Oakville project is - TopicsExpress



          

The auditor found the cost of killing the Oakville project is “significantly more than may have been necessary” because of a number of what she called “questionable decisions” by the premier’s office and the Ministry of Energy.“Hydro customers will be paying higher rates for electricity in the future as a result of not only the cancellation of the Oakville contract, but also because of the OPA not being able to take full advantage of the terms within the contract that may well have enabled the province to get a better deal,” she said. - See more at: ottawacitizen/news/Cost+killing+Oakville+plant+815M+auditor+says/9012377/story.html#sthash.xb3dzCtk.dpuf
Posted on: Wed, 09 Oct 2013 01:42:48 +0000